A11 Traffic Management

On local roads approaching the Fiveways roundabout, we will have temporary 40mph speed restrictions placed on them 24 hrs per day. In addition, the A11 northbound leading to the roundabout will have the existing 50 mph speed restriction moved further back, to allow a further reduction of the 40 mph limit.
 
There will be an ongoing speed restriction of 40mph 24hrs per day between Fiveways roundabout [Barton Mills] and London Road [Thetford] roundabout.
 
The C616 is now permanently closed at the junction with the A11. Access is still possible from the A1065 [Brandon Road]
 
There will be a temporary speed restriction of 30mph imposed on the Center Parcs side of the B1106. Exact date will be advised later.
 
The maximum length of road affected by temporary traffic signals will be restricted to 500 metres and minimum spacing between sets will be 2.5 km. 
 
Temporary speed limit signage is installed for the roundabout and the A11 northbound , A1101 Bury Road, A1101 Mildenhall road and A1065 Brandon Road approaches to the roundabout.
 
W/C 12h August.
•         Days:
o   A11 Plant crossing operation Olly’s track. From Monday to Saturday 7am to 7pm.
o   A11 Plant crossing operation at Chalk Hall. Monday to Saturday 7am to 7pm.
o   A11 Plant crossing operation at Gibson’s. Monday to Saturday 7am to 7pm (periodic use only).
o   B1106 Plant crossing operation. Monday to Saturday 7am to 7pm.
•         Nights:
o   A11 northbound two way portable traffic signals at the Gibson’s Accommodation Overbridge construction area; Wednesday 14th August to Friday 16th August
o   A11 southbound two way portable traffic signals at/near to the Chalk Hall Farm Accommodation Bridge construction area; Wednesday 14th August to Friday 16th August
o   A11 north & southbound inner or outer roundabout lane closure to the Barton Mills (Fiveways) roundabout, including all approaches to the roundabout; Monday to Friday 7pm to 6am.
 
 
Look Ahead W/C 19th August.
•         Days:
o   A11 Plant crossing operation Olly’s track. From Monday to Saturday 7am to 7pm.
o   A11 Plant crossing operation at Chalk Hall. Monday to Saturday 7am to 7pm.
o   A11 Plant crossing operation at Gibson’s. Monday to Saturday 7am to 7pm (periodic use only).
o   B1106 Plant crossing operation. Monday to Saturday 7am to 7pm.
•         Nights:
o   A11 southbound two way portable traffic signals north of the Elveden Crossroads for BT Cable Pulling (switch to northbound carriageway will be required);  Monday 19th to Wednesday 21st August (Wednesday is a contingency date and will be cancelled if not required).
 
o   A11 southbound two way portable traffic signals at the Gibson’s Accommodation Overbridge construction area; Thursday 22nd August (to be confirmed).
o   A11 southbound two way portable traffic signals at Canada Farm entrance (near to Gibson’s Lodge); Thursday 22nd August (to be confirmed).
o   A11 southbound two way portable traffic signals sections at/near to the  NMU Underpass construction area; Thursday 22nd August (to be confirmed).
For the above, only one portable traffic signal lane restriction will be installed at any one time, and will be removed before moving to the next work location.
 
o   A11 north & southbound inner or outer roundabout lane closure to the Barton Mills (Fiveways) roundabout, including all approaches to the roundabout, for roundabout and island reconstruction works; Monday to Thursday 7pm to 6am.
 
•         Late Summer August Bank Holiday Highways Agency Embargo:
o   No day or night time temporary traffic management lane restrictions allowed from 06.00 Friday 23rd to 00.01 Tuesday 27th August. Temporary speed limit, narrow lanes , B1112 and C616 road closure to remain in place for safety.