A11 Roadworks Update

Week commencing  30th September 2013
 
Days
 
A11 plant crossing at Chalk Hall Farm two traffic signals manually operated, Monday to Saturday 7am to 7pm [periodic use only]
 
A11 plant crossing at Gibson’s Lodge two way traffic signals manually operated, Monday to Saturday 7am to 7pm [periodic use only]
 
A11 plant crossing Olly’s track two way traffic signals manually operated, Monday to Saturday 7am to 7pm.[periodic use only]
 
B1106 plant crossing operation Monday to Saturday 7am to 7pm.
 
A11 Plant crossing operation at A11/C616 Monday to Saturday 7am to 7pm.
 
 
Nights
 
A11 north and/or south bound two way portable traffic signals various locations Monday to Friday as and when required.
 
A11 inner or outer roundabout lane closure to the Barton Mills [Fiveways] roundabout, including all approaches to the roundabout, for island reconstruction, Monday to Friday 7pm to 6am.
 
A11 north bound approach and southbound departure lane narrowing at Thetford roundabout for re-construction/re-alignment works. Monday to Friday 7pm to 6am
 
A11 northbound full carriageway closure red Lodge to Barton Mills [Fiveways] for Fiveways reconstruction re-surfacing 10pm Friday 4th October until 6am Monday 7th October. As part of this road closure there will be
 
A lane 1 closure on the A14 east bound on the approach to junction 38 Waterhall Interchange with the A11
 
No north bound access onto the A11 from either end of Newmarket Road.
 
No north bound access onto the A11 from Barton Mills, The Street.
 
A1101 Bury Road will be closed to traffic in either direction from 100 metres prior to the Barton Mills Fiveways roundabout]